Simple Car Battery Production Line Full Automatic Double Station Envelop Tester
1. Device functions
It is mainly used for square aluminum battery shell envelopment, including automatic battery feeding, code scanning, shell envelopment, insulation patch, appearance size detection, insulation test, blanking, etc. This envelopment line is automatic envelopment line, there is unqualified battery outflow channel, and the relevant detection data is automatically recorded.
2. Equipment process parameters requirements
project | specifications |
Thickness measuring pressure | Adjustable from 200 to 800Kgf, accuracy ±20kgf, resolution 0.1 KGF |
Width measuring pressure | Adjustable from 5 to 20Kgf, accuracy ±1kgf, resolution 0.1 KGF |
Height measurement pressure (pole column and pole column) | 0.5~5Kgf adjustable, accuracy ±1kgf, resolution 0.1kgf |
Dimensional measurement accuracy | ±0.01mm, with a resolution of 0.001mm |
Single machine capacity | 12 PPM or higher |
An optimal rate | 99.5% or higher |
Scrap rate | 0.01% or less |
Device rotation rate | ≥98% (failure caused by equipment only) |
Mean fail-free running time MTBF | 5 hours or more |
The machine noise | ≤75dB (one meter from the outer wall of the equipment) |
The engine bearing | 1.2 T / ㎡ or less |
3. Electrical parameters of the equipment
3.1 basic parameter requirements
Line body name
|
The compressed air | vacuum | The environment temperature | Environmental humidity | The ground bearing | Equipment power |
Double-station envelope testing machine |
After 28 m/h / 0.4 0.7 MPa | After 15 m/h - 80 KP ~ - 90 KP | 20 ~ 35 ℃ | 5 ~ 55% HR | > 800 kg / ㎡ | AC380V, three-phase; Voltage fluctuation is less than ±10%; Power supply: 30KVA |
Line body name | Number of air outlets for compressed air (green) | Power outlet (yellow) | Vacuum outlet (blue) | Specification (mm) |
Double-station envelope testing machine |
|
|
|
|
1. New equipment promise
Our company guarantees that the goods provided to customers are brand new, complete and unused equipment.
2. Confidentiality commitment
Our company promises that without the written permission of any party, the other party's related drawings, technical information, business information and other business secrets and technical secrets must not be leaked to third parties in any way.
3. After-sales service commitment
(1) Two months from the date of shipment of the equipment, Party B is responsible for non-human faults in a timely and free warranty within one year (when the equipment is faulty, the after-sales service staff will respond within 2 hours after receiving the notification. According to the situation, personnel must be in place within 48 hours. No later than 60 hours, to ensure the continuity of production by the buyer;
(2) After the equipment has passed the warranty period, if there is a problem, the two parties communicate and deal with it. If necessary, after-sales personnel will be sent to repair it, and only the cost will be charged. Zh
(3) During the warranty period stipulated in the contract and technical agreement signed by the two parties, the company will provide a warranty for quality problems that are not caused by human damage during the normal use of our products.